§ 13.20.030. ENGINEERING DRAWINGS.  


Latest version.
  • A. The City Engineer and the City Council shall approve all engineering drawings and construction plans prior to the commencement of any work by the subdivider All required supplementary engineering studies or tests as required by the City Engineer and/or the City Council shall be approved prior to final plat approval.
    B. All required engineering studies and exhibits shall be prepared by qualified and legally registered or certified engineers or engineering firms.
    C. Contractors engaged by the subdivider to install required improvements shall be licensed and registered as required by state or local law.
    D. It may be desirable, during construction of improvements, for the subdivider to modify some standards and specifications of the approved engineering drawings. In this event, the subdivider shall, prior to making such modifications, submit a schedule of the modifications with reasons of necessity to the City Engineer.
    E. At the completion of all new construction relating to street or utility improvements, the subdivider shall submit “as-built drawings” to the City Engineer prior to approval of the work by the City Engineer.
    (Prior Code, § 12-4-3 (part)) (Ord. 08-913, passed 3-11-2008)